Can we sign the equipment order today?
European Commission · EUR-Lex
A project team is about to commit to an investment. The scheme applies the ordinary GBER incentive-effect rule.
Question to settle
The supplier wants a binding order that makes the investment irreversible. The team has a quotation, a feasibility study and an unsubmitted aid form. What should happen first?
Choose an answer to see the reasoning
Sign now and apply before the first invoice.
Reconsider this choice · The binding order starts the investment on these facts. A later invoice or payment cannot move that date.
File before signing and check the scheme’s start conditions.
Correct · A quotation or preparatory feasibility study generally leaves the investment decision open. The proposed order would commit the team.
Next step
Submit the required written application before committing and retain dated proof of filing. Include the undertaking’s name and size, project description, dates, location, costs, aid type and public funding needed. Check whether the scheme also requires a decision or permission to start.
Status and scope
Investment example under Articles 2(23) and 6(2). Check the scheme’s legal basis, exceptions and any stricter filing conditions.
Official passages
- Commission Regulation (EU) No 651/2014 Articles 2(23), 6(1)–(2) and 6(5)
- Service public de Wallonie · RGEC Conditions générales du RGEC
Related guides
- ERDF equipment · when can a partner commit to a purchase?EFRO Vlaanderen · VLAIO · The Flemish and Limburg calls finance research and demonstration equipment. VLAIO lists €6 million for the Flemish call and €2.25 million for the Limburg call. Each is a budget for the entire call.
- R&D feasibility studyVLAIO · A business assesses feasibility before a potential follow-on R&D project.
- Technical feasibility studyInnoviris · A company examines technical feasibility in-house or with a specialist provider.