← Dates required in a notification
3° la date de début attendue et la date envisagée de fin du projet ou programme.
WIB 92 / CIR 92 · art. 275³, § 3, 3° · 2022 edition · p. 4 
3° de verwachte aanvangsdatum en de vooropgestelde einddatum van het project of programma.
WIB 92 / CIR 92 · art. 275³, § 3, 3° · 2022 edition · p. 4
Two dates on the notification
Questions across measures · Exercise
A company notified a project before development began. Its copy includes the expected start but leaves the envisaged end blank. Identity and description are supplied.
Sources for this question
- CIR 92, art. 275³Source in another language · Français
§3, registration particulars, 1°–3°, in particular 3° • PDF p. 4
BELSPO extract, 2022 edition. Check later changes for the relevant period.
Source details - BELSPO · e-News Fiscal · 2023/2Source in another language · Français
Notice on timing • application from 1 August 2023
Source checked on 25 November 2026.
Source details
Original wording
The 2022 legal extract identifies the two dates to give. BELSPO’s separate notice addresses when the notification must be made.
Notification of a project or programme · Français

WIB 92 / CIR 92 · art. 275³, § 3, 3° · 2022 edition · p. 4
Notification of a project or programme · Nederlands

WIB 92 / CIR 92 · art. 275³, § 3, 3° · 2022 edition · p. 4
This exercise examines one condition. The overall outcome needs a separate assessment of the full file.