A manufacturing SME with its own legal personality can apply directly for a circular design project. Belgian locations eligible under the common rules are the Liège and Verviers districts and the province of Limburg. A registered office or establishment in the area qualifies if the project is carried out in the Meuse–Rhine area. Wallonie Design or EKLO handles Walloon files. The project normally lasts up to nine months. POM Limburg or UCLL handles Flemish files.
Question to settle
A Verviers SME has tested a repairable industrial component at technology readiness level 5 (TRL 5). It explains how the voucher would take it to TRL 6. Eligible work totals €96,000 and has received no other regional or EU subsidy. What funding can it plan for?
Choose an answer to see the reasoning
Seek €48,000 and use the advance to pay for the tests.
Reconsider this choice · Half of €96,000 is €48,000. The ceiling is €40,000, and the scheme rules out advances and instalments.
Request up to €40,000, cover at least €56,000 and plan cash flow until the results are verified.
Correct · The October rules cap support at 50% of eligible costs and €40,000. A TRL 5 file can qualify if it demonstrates progress to at least TRL 6. Projects already at TRL 6 or above get priority. Payment depends on verified deliverables.
Wait until TRL 7. Only then can the SME apply.
Reconsider this choice · TRL 6–9 is the normal range. Section 3.2 of the second-call regulation permits the documented TRL 5 exception. TRL 4 and below are ineligible.
Next step
Budget €20,000 or more in eligible costs. Check the de minimis declaration, any other grant on the project and the one-voucher limit per SME. Use the programme’s online application in English, with both signed forms. Contacting the regional partner is recommended. Wait for written start confirmation. The project starts on the first day of the following month unless a postponement is approved. For example, a start confirmation received on 12 May sets 1 June as the normal start. To move it, email the reasons to both the regional K2C project partner and lead partner UCLL by 1 June. The regional partner must confirm the new date in writing. The maximum postponement is three months.
Status and scope
The second call is open. The Walloon notice sets 1 March 2027 at 23:59 for applications. The formal second-call regulation was updated on 20 October 2026.
Official passages
- Key 2 Circularity – Voucher scheme · Subsidy regulation, 20 October 2026 §3.2 · minimum budget, €40,000 ceiling, TRL 5 exception, priority and nine months.
- Key 2 Circularity – Voucher scheme · Subsidy regulation, 20 October 2026 §2 · maximum one voucher per SME, €10,000–€40,000 and co-financing.
- Key 2 Circularity – Voucher scheme · Subsidy regulation, 20 October 2026 §3.1 · separate legal entity, financial standing, de minimis and other subsidies on the project.
- Key 2 Circularity – Voucher scheme · Subsidy regulation, 20 October 2026 §3.1 · Belgian eligible districts, Limburg and establishment rule.
- Key 2 Circularity – Voucher scheme · Subsidy regulation, 20 October 2026 §4.1 and preceding paragraph · no advances or instalments, online English file and signed de minimis declaration.
- Key 2 Circularity – Voucher scheme · Subsidy regulation, 20 October 2026 Second-call regulation as revised on 20 October 2026, §§4.4–5.1, pp. 15–16 · regional decision, start email, default date, both recipients, request deadline, three-month limit and written approval.
- Interreg Meuse-Rhine · K2C Investment Vouchers How to apply · second-call dates, direct application link and separate introductory meeting.
- Wallonie Design · Investment Voucher Arrondissements de Verviers et de Liège, version anglaise du règlement faisant foi et accès à l’entretien préalable.
- Circular Wallonia · Deuxième appel Key 2 Circularity Avis du 10 novembre 2026, rubriques « Circular Boost » et « Investment Vouchers » · 1er mars 2027 à 23h59 pour chacune des candidatures.
Application calendar for Belgian research funding
Related guides
- What can a selected construction consortium put in its budget?SPW Économie, Emploi, Recherche · Circular Wallonia · A Namur company and several building contractors want to test a shared system for reusing components. Suppose their proposal was selected under the second Boost4Circularity call. Their €80,000 pilot needs a testing partner, common specifications and staff training.
- STIPP – experimental development by SMEsInterreg Meuse–Rhine · STIPP · At least two independent SMEs from two Member States in the programme area jointly develop a market-oriented product, process or service. Call 4 allowed work at TRL 4–5 if the project reached at least TRL 6.
- Call 8 · build a partnership from East BelgiumInterreg Meuse-Rhine · Provincie Limburg (NL) · Call 8 supports practical cross-border innovation in circular bio-based value chains and the economic use of technologies linked to the Einstein Telescope. The programme asks applicants to involve SMEs. Belgian Limburg, Liège and Belgium’s German-speaking Community are in the core area.
- Circular Boost · secure expert time for a first proof of conceptKey 2 Circularity · Wallonie Design / EKLO · Interreg Meuse-Rhine · In the Liège and Verviers districts, six manufacturing SMEs can receive free coaching to develop and validate a circular design concept targeting TRL 5–7. The regional partner values the service at €17,500 per selected business. It combines individual work and two cross-border group sessions over up to eight months.
- Technology voucherSPW Recherche · A Walloon SME uses an eligible centre to validate a new product, process or service scientifically. SPW distinguishes this service from intellectual-property advice.