BELSPO asks for more information. When does the three-month period start?
BELSPO
A Belgian engineering firm registered its R&D project before work began. It then asked BELSPO for a binding opinion. Within the first month, BELSPO asked which technical uncertainty the team had investigated.
Question to settle
BELSPO receives the last of the information it requested on 12 February. On which day does the normal period for delivering its opinion begin?
Choose an answer to see the reasoning
The day after the original request arrived
Reconsider this choice · That date starts the one-month completeness check. A timely request for information changes when the file is deemed complete.
13 February, the day after the file became complete
Correct · Receiving the last requested explanation completes the file on 12 February. The three-month period starts the next day. The applicant and BELSPO can agree a different period.
The day after BELSPO sends its confirmation
Reconsider this choice · The confirmation records completeness. Article 95³ ties the start to when the application is deemed complete.
Next step
Keep the original request, the questions and proof of receipt of the last answer. BELSPO confirms completeness within 14 days of receiving all requested additions. If it asks nothing during its one-month check, the file is deemed complete when that month expires.
Status and scope
Article 95³ of the Royal Decree implementing the Income Tax Code sets the timetable for BELSPO’s opinion on payroll withholding relief.
Official passages
- Artikel 95³, KB/WIB 92 p. 1 · volledigheid van de aanvraag, bijkomende uitleg en termijn voor het advies
- Article 95³, AR/CIR 92 p. 1 · demande réputée complète, délai de communication et accord sur le délai
- Article 95^3, AR/CIR 92 (revenus 2026) Art. 95³ · complétude du dossier et délai de communication
- Artikel 95^3, KB/WIB 92 (inkomsten 2026) Art. 95³ · volledigheid en adviestermijn
Related guides
- Payroll withholding for researchersBELSPO · FOD Financiën / SPF Finances · An employer may retain part of the tax withheld under the applicable branch of article 275³. For a project-based claim, the work, qualifications and time actually spent on research matter.
- Hasselt · A list of projects without a programme objectiveRechtbank van eerste aanleg Limburg, afdeling Hasselt · 11A kamer · The employer listed projects with short descriptions. The court could find neither an industrial research objective for the programme nor evidence linking those projects to it. A BELSPO certificate and subsequent opinion were evidence the court could weigh. It dismissed the employer’s claim.